The following is a description of the purpose, deliverables, and attendees for project meetings.
Project Feasibility
Project kickoff meeting with regulators
- Meeting Preparation – Agenda Required
- Confirm Authority Having Jurisdiction (AHJ)
- Demonstrate Land Ownership
- Infrastructure Ownership/Condition
- Change in Use/Occupancy
- Outside Agency Involvement
- Other Environmental Permitting Agencies
- Post Meeting/Deliverables
- Meeting Minutes and Final Feasibility Report provided by Planning, Space, and Real Estate
- Building Code Department Role is Known and Confirmation as the AHJ
- Bluebeam All Call Stakeholder Session
- No Bluebeam
- Party Responsible for Scheduling
- Planning, Space, and Real Estate
- Required Attendees
- Capital Project Management
- Planners/ Planning, Space, and Real Estate (Leader)
- Engineers
- Building Code Department Leadership
- Building Code Department Plan Reviewers
Pre-Design Meeting
Near the end of pre-design but prior to finalizing
- Meeting Preparation – Agenda Required
- Prepare Meeting Agenda and Following Documents:
- Scope/Schedule/Budget (Valuation)
- Preliminary Code Analysis
- Site Plan (fire department apparatus roads and hydrants)
- Preliminary Floor Plans/Cross Section
- Architect or Engineer of Record prepared to discuss/review the following:
- Applicable Codes
- Existing Record Drawings (if applicable)
- Jurisdictional Authority
- Outside Agency involvement: Minnesota Department of Health, Minnesota Department of Labor and Industry, High Pressure Steam, Elevators, Modular/Prefab Building and Structures
- Alternative Design, Materials or Methods
- Operational licenses and/or permits
- Utilities (Private or Public)
- Prepare Meeting Agenda and Following Documents:
- Post Meeting/Deliverables
- Meeting minutes provided by the Architect or Engineer of Record
- Bluebeam All Call Stakeholder Session
- Building Code Department invited but not expected to comment
- Party Responsible for Scheduling
- Capital Project Management
- Required Attendees
- Capital Project Management
- Planners/ Planning, Space, and Real Estate (Leader)
- Architect (Leader)
- Building Code Department Leadership
- Building Code Department Plan Reviewers
- Building Code Department Fire Marshals
Schematic Design 1st Meeting
Beginning of Schematic Design
- Meeting Preparation – Agenda Required
- Prepare Meeting Agenda and Following Documents:
- Scope: clear description of nature of work: New, Addition, Renovation)
- Project Schedule
- Preliminary Code Analysis (state applicable main governing code: IBC or MCCEB path)
- Site Plan
- Survey (if necessary)
- Floor Plans/Cross Section
- Architect or Engineer of Record
- Previous pre-design decisions
- SAC/Industrial SAC
- Anticipated Project Phasing / Phased Occupancy
- Energy Code Pathway and related requirements (Commissioning, Testing and Verification)
- Permitting Submittal Documents
- Chemical Inventory (MAQs, Control Areas, storage, ventilation)
- Outside Agency involvement: Minnesota Department of Health, Minnesota Department of Labor and Industry, High Pressure Steam, Elevators, Modular/Prefab Building and Structures
- Alternative Design, Materials or Methods
- Special Provisions / Chapter 4
- Special Inspections
- Special Project Requests
- Prepare Meeting Agenda and Following Documents:
- Post Meeting/Deliverables
- Meeting minutes provided by the Architect/Engineer of Record
- Bluebeam All Call Stakeholder Session
- Not Applicable
- Party Responsible for Scheduling
- Capital Project Management
- Required Attendees
- Capital Project Management
- Planners/ Planning, Space, and Real Estate (Leader)
- Architect (Leader)
- Building Code Department Plan Reviewers
- Building Code Department Fire Marshals
Schematic Design 2nd Meeting
End of Schematic Design (95% Complete)
- Meeting Preparation – Agenda Required
- Prepare Meeting Agenda & Following Documents:
- Updated Code Analysis
- Architect or Engineer of Record is prepared to discuss/review the following:
- Any changes to the project scope
- Documents reflect regulatory requirements
- Prepare Meeting Agenda & Following Documents:
- Post Meeting/Deliverables
- Meeting minutes provided by the Architect/Engineer of Record
- Bluebeam All Call Stakeholder Session
- Building Code Department invited -not expected to comment
- Party Responsible for Scheduling
- Capital Project Management
- Required Attendees
- Capital Project Management
- Architect (Leader)
- Building Code Department Leadership
- Building Code Department Plan Reviewers
Design Development 1st Meeting
If Needed beginning of Design Development – Consult with Building Code Department Leadership
- Meeting Preparation – Agenda Required
- Prepare Meeting Agenda and Following Documents:
- Project review of existing documents and confirmation documents reflect regulatory requirements
- Prepare Meeting Agenda and Following Documents:
- Post Meeting/Deliverables
- Meeting minutes provided by the Architect/Engineer of Record
- Bluebeam All Call Stakeholder Session
- Not Applicable
- Party Responsible for Scheduling
- Capital Project Management
- Required Attendees
- Capital Project Management
- Architect (Leader)
- Engineers
- Building Code Department Leadership
- Building Code Department Plan Reviewers
Design Development 2nd Meeting
End of Design Development (95% Complete)
- Meeting Preparation – Agenda Required
- Prepare Meeting Agenda and the following documents:
- Finalize Scope
- Finalize Code Analysis
- Finalize Energy Code Design Compliance Pathway
- Owner selected Verifications and Testing Provide and Commissioning Agent if required (Energy Code Commissioning Roles and Responsibilities understood)
- Finalize phasing documents
- Finalize SAC documentation
- Specific project and code questions directed to specific Building Code Department Staff /Trade Discipline
- Architect or Engineer of Record is prepared to discuss/review the following:
- Project scope/overview with all Building Code Department staff
- Conduct a page turn of prepared documents
- Confirmation documents reflect regulatory requirements
- Equipment (Listings and certifications)
- B Occupancy Laboratories (containing hazardous materials):
- Design to IBC Table 414.2.2 or 414.2.6 Minnesota Amendment for Control Areas
- Hazardous Material Inventory Statement (HMIS): Chemical Types and MAQs anticipated per Control Area(s) design/formatted to IBC Table 307.1.(1) and 307.1.(2)
- Identify Control Area(s) and Boundaries
- State Mechanical Ventilation and Hazardous Exhaust rates for process and types of chemicals
- Prepare Meeting Agenda and the following documents:
NOTE: Expectation is all plans (including MEP and civil plans) have been completed prior to this meeting
- Post Meeting/Deliverables
- Meeting minutes provided by the Architect/Engineer of Record
- SAC documentation ready for BCD cursory review and pending Metropolitan Council Environmental Services (MCES) submission
- Alternative Design, Materials and Methods (ADMM) are ready for BCD review and pending approval to be incorporated with CD drawings
- Bluebeam All Call Stakeholder Session
- Building Code Department invited -not expected to comment
- Party Responsible for Scheduling
- Capital Project Management
- Required Attendees
- Capital Project Management
- Architect (Leader)
- Engineers
- Building Code Department Leadership
- Building Code Department Plan Reviewers
- Building Code Department Trade Inspectors
- Building Code Department Fire Marshals
Construction Documents
End of Construction Documents (95% complete)
- Meeting Preparation – Agenda Required
- Prepare meeting Agenda and following documents
- Completed set of construction “Permit Construction Documents”
- Architect or Engineer of Record is prepared to discuss/review the following: Deferred permit submittals (site staging/logistics, contractors budget/GM, Etc.)
- Prepare meeting Agenda and following documents
- Post Meeting/Deliverables
- Meeting minutes provided by the Architect/Engineer of Record
- Special Inspection and Testing Forms are enroute for signatures and BCD final approval
- Energy Design has been completed and includes the following:
- Function Performance Testing (FTP)
- Energy Prescriptive/Performance Pathway Compliance documentation (COMcheck, Budget Cost Analysis)
- Bluebeam All Call Stakeholder Session
- Building Code Department invited -not expected to comment
- Party Responsible for Scheduling
- Capital Project Management
- Required Attendees
- Capital Project Management
- Architect (Leader)
- Engineers
- Building Code Department Leadership
- Building Code Department Plan Reviewers
- Building Code Department Trade Inspectors
- Building Code Department Fire Marshals
Informal Discussions
Architect or Engineer of Record Team or BCD to meet as necessary
- Meeting Preparation – Agenda Required
- Concept Discussion
- Bluebeam All Call Stakeholder Session
- Not applicable
- Party Responsible for Scheduling
- Informal